arrowHome arrow News arrow Topping-out ceremony at a height of 160 m
Monday, 06 September 2010
Heitkamp IKB


Newsticker

  ::Groundbreaking on the Weinberg campus in Halle/Saale
3rd September 2010

The Halle branch of Heitkamp Ingenieur- und Kraftwerksbau GmbH was entrusted in August 2010 by the local Technology Park TGZ with the construction of another multi-purpose building for the research and development activities of small- and medium-size companies.

The overall investment volume of TGZ Halle for this project amounts to ca. 3 million euros.



read more

  ::Reinforced concrete for high-rise sugar silo
26th June 2010

In June 2010, Heitkamp Ingenieur- und Kraftwerksbau GmbH (HIKB) successfully completed the reinforced concrete works for a new sugar silo in Nykøbing Falster, Denmark.

In an internal cooperation between the Heitkamp branches of Herne and Halle, the works for the outer reinforced concrete shell of the silo with a diameter of 44.30 m and a height of approx. 50.00 m as well as for the attached 60 m-high elevator and staircase tower were completed in only six months after they started in mid-January 2010 using the slip-form construction method.
 



read more

  ::Pouring of foundation concrete in Lünen
27th May 2010

Presently, the concreting operations for the first foundation slab section of the future 70 m-high fly-ash silo on the Trianel power plant site in Lünen are under way.


read more

  ::Further milestone for the Wusterwitz Lock project
3rd May 2010

At the end of March, the Rostock branch was able to report the completion of the building pit. Four weeks later, another milestone was reached with the large-scale concrete placing operation for part of the foundation on April 27 and 28.

The placing operation comprised ca. 2,700 cubic meters of watertight concrete.


read more

  ::Large-scale concrete placing operations in the Lünen coal-fired power plant
22nd February 2010

Further milestone in the construction of the new Trianel coal-fired power plant in Lünen:

The concreting work for the turbine table foundation will be carried out on schedule on Feb. 24, 2010.

The concrete for the turbine table of the 800 MW turbine in the new coal-fired power plant in Lünen will be placed on Feb. 24, 2010.
 


read more
 
Topping-out ceremony at a height of 160 m Print E-mail
template_luenen_017th December 2009

The completion of the cooling-tower shell on the Trianel construction site in Lünen was celebrated with a topping-out ceremony in December 4, 2009.







luenen_02_bigAt a height of 160 m, the representatives of the developer Trianel and the main contractor Siemens drank to the timely completion of the works with the staff and construction workers of Heitkamp Ingenieur- und Kraftwerksbau GmbH. The topping-out crown was raised at 12:30 pm.

The topping-out speech was delivered by Heitkamp site foreman Martin Lehmann. At the end of the speech, he threw his glass into the opening of the tower.

 